Project Overview
Location:
She-Oak Lane, Casuarina, NSW 2487
System Components
Inverters: 2 x Growatt 5000 TL-X
Solar Panels: 36 x 350W
System Capacity:
Total System Capacity: 12.6 kW (2 inverters x 5 kW each + 36 panels x 0.35 kW each)
Installation Date:
The solar energy system was commissioned on 19/01/2021.
System Design and Configuration:
Growatt 5000 TL-X Inverters:
The Growatt inverters were chosen for their efficiency and compatibility with the two-phase power configuration. String inverter configuration ensures optimal energy conversion.
Solar Panels:
The 36 solar panels, each with a capacity of 350 watts, were strategically positioned to maximize exposure to sunlight. Monocrystalline cells contribute to enhanced energy production.
Performance Analysis
Energy Production:
Regular monitoring of the system’s performance demonstrates consistent energy production.
Efficiency:
Assess the efficiency of the Growatt inverters and solar panels under various conditions.
Environmental Impact
Carbon Footprint Reduction:
The solar installation at Casuarina, NSW 2487 has significantly reduced reliance on conventional energy sources, leading to a notable reduction in carbon emissions.
Maintenance and Monitoring:
Remote Monitoring:
The Growatt inverters’ remote monitoring capabilities facilitate real-time performance tracking.